NorPower were contracted by SSE to construct a Trident-based 132kV line between Peterhead power station and St Fergus switching station. The project included installation of carbon fibre core conductor which is believed to be the first use of ACCC conductor on a fixed insulator wood pole design in the world. All previous installations of ACCC utilised suspended insulator types.